Metropolitan Region Development Authority / Collector’s Sanctioning

The Building Permission Department works under the provisions of Maharashtra Metropolitan Region Development Authority Ordinance of 2016 and those under the Maharashtra Regional and Town Planning Act, 1966. For building any industrial plant it is mandatory to seek permission from Regional Development Department from the collector’s office.

Documents Required

  1. Non-Agriculture (NA) permission
  2. Site Visit Report
  3. Zone Certificate
  4. Zone Map
  5. Gram Panchayat NOC
  6. Ferfar From 1949 (Mutation Entries From 1949)
  7. 7/12 extract from 1949
  8. Following NOCs required if applicable
    1. Tree Authority
    2. Storm Water and Drain Department
    3. Sewerage Department
    4. Hydraulic Department
    5. Environmental Department (concerned with debris management)
    6. Consent to Establish OR Consent to Operate
    7. Ancient Monument Approval
    8. Airports Authority of India
    9. Traffic and Coordination Department
    10. CFO (fire clearance)
    11. Structural Plan Approval

*Note: Additional Documents may be required For More Details Please Contact

Stages Involved in sanctioning Plan:

Stage 1: Collection of all said documents.

Stage 2:Application drafting and submission to DM.

Stage 3: Follow ups with the DM office to resolve queries raised by DM.

Stage 4:Approval of building plan

What you get by plan sanctioning service through Kishkinda Engineering Services.

Collection of all the supporting documents

Making and submission of the proposal to the concerned authority

Follow ups with DM Office

Reply to queries raised by DM Office

Building Plan approval with Stamp