The Building Permission Department works under the provisions of Maharashtra Metropolitan Region Development Authority Ordinance of 2016 and those under the Maharashtra Regional and Town Planning Act, 1966. For building any industrial plant it is mandatory to seek permission from Regional Development Department from the collector’s office.
*Note: Additional Documents may be required For More Details Please Contact
Stage 1: Collection of all said documents.
Stage 2:Application drafting and submission to DM.
Stage 3: Follow ups with the DM office to resolve queries raised by DM.
Stage 4:Approval of building plan
Collection of all the supporting documents
Making and submission of the proposal to the concerned authority
Follow ups with DM Office
Reply to queries raised by DM Office
Building Plan approval with Stamp